Coordinating Distributed Energy Resources for Reliability can Significantly Reduce Future Distribution Grid Upgrades and Peak Load

14 Jun 2023  ·  Thomas Navidi, Abbas El Gamal, Ram Rajagopal ·

Current DER coordination schemes, such as demand-response and VPPs, aim to reduce electricity costs during peak demand events with no consideration of distribution grid reliability. We show that coordinating DERs for grid reliability can significantly reduce both the infrastructure upgrades needed to support future increases in DER and electrification penetrations and peak load. Specifically, using a power flow driven simulation-optimization methodology, we compare the potential reliability improvements with a perfect-foresight centralized DER controller that minimizes reliability violations to a local controller that minimizes consumer electricity cost. We find, for example, that by 2050 with local control, on average 81% of the transformers in a distribution grid experience violations, compared to 28% with centralized control, which simultaneously reduces peak load by 17%. These reductions are achieved with only 5.1% increase in electricity cost. These findings suggest that future incentives for DER adoption should include reliability coordination.

PDF Abstract
No code implementations yet. Submit your code now

Tasks


Datasets


  Add Datasets introduced or used in this paper

Results from the Paper


  Submit results from this paper to get state-of-the-art GitHub badges and help the community compare results to other papers.

Methods


No methods listed for this paper. Add relevant methods here